Dear Atty. Gab
Musta Atty! My name is Mario Rivera, and I’m in a very stressful situation with the contractor building our family’s dream home in Antipolo. We signed a contract with “SolidBuild Construction” with a clear completion date of December 15, 2023, and a penalty clause of Php 10,000 for every day of delay.
It’s now been several months past the deadline, and the house is still not finished. When I brought up the penalty, SolidBuild refused to pay, claiming the delays were my fault. First, they said the ground was unexpectedly rocky and required extra time for excavation, something they claim they couldn’t have known. Second, they are blaming me for a few minor changes I requested, like moving a power outlet and adding an extra water line in the garden. They claim these small changes disrupted their entire schedule.
Finally, there was a one-month delay in securing the building permit. Our contract stated they would process all necessary permits, but they argue that I should have been more proactive in following up with the local government office. To make matters worse, the paint job they did on the exterior is already peeling, but they won’t fix it unless I pay them more. They are demanding I pay the final 10% retention fee to get them to finish the job. I feel like they are just making excuses. Can they really avoid the penalties for being so late? Am I obligated to pay the retention fee even with the poor workmanship? I would be very grateful for your guidance.
Respectfully,
Mario Rivera
Dear Mario,
Thank you for reaching out. I understand how frustrating it is when your dream home project turns into a source of stress and conflict. The situation you’ve described is quite common in construction projects, and Philippine law provides a framework for resolving these disputes.
In essence, liability for delays in a construction contract hinges on who is at fault. A contractor is not automatically liable for all delays. If a delay is proven to be justifiable—caused by unforeseen circumstances or by the owner’s own actions—the contractor may be entitled to a time extension. However, the contractor also has clear obligations regarding workmanship and providing the necessary resources to complete the project. Let’s break down the principles that apply to your situation.
Building a Case: Unpacking Delays and Defects in Construction Contracts
In a construction agreement, both you (the owner) and the contractor have reciprocal obligations. The contractor is obliged to build the structure according to the agreed plans and timeline, while you are obliged to pay the contract price. When delays occur, the crucial task is to determine the cause. The penalty clause you mentioned is legally referred to as liquidated damages, which are amounts pre-agreed upon by the parties to be paid in case of a breach, such as a delay.
Art. 2226. Liquidated damages are those agreed upon by the parties to a contract, to be paid in case of breach thereof. (Civil Code of the Philippines)
This provision validates the Php 10,000 per day penalty in your contract. However, for it to be enforceable, the delay must be attributable to the contractor. The contractor’s claims—unforeseen rocky ground, your change orders, and permit issues—are attempts to establish that the delays were justifiable and not their fault.
Let’s examine their arguments. First, regarding the unexpectedly rocky soil, a contractor is generally expected to have inspected the site and to have factored in reasonably foreseeable conditions into their timeline and bid. If the ground condition was truly exceptional and could not have been discovered through a standard site inspection or soil test, it might be considered a justifiable cause for delay. However, if the contractor was negligent in assessing the site, the responsibility falls on them. The law recognizes that liability arising from negligence can be adjusted by the courts based on the circumstances.
Art. 1172. Responsibility arising from negligence in the performance of every kind of obligation is also demandable, but such liability may be regulated by the courts, according to the circumstances. (Civil Code of the Philippines)
This means if both parties contributed to a delay, a court can equitably apportion liability. For instance, while the contractor is responsible for having functional equipment, an unforeseen site condition they did not cause could be grounds for a partial extension. Second, your change orders for moving a power outlet and adding a water line can indeed be a basis for a time extension. Even minor changes require adjustments that can affect the construction schedule. The key is whether the time extension the contractor is implicitly claiming is proportional to the work required for these changes. The burden is on them to prove how these minor alterations caused a multi-month delay.
Regarding the building permit, your contract is paramount. If the agreement explicitly states that SolidBuild Construction is responsible for processing permits, then they are accountable for delays arising from their failure to do so efficiently. Their argument that you should have followed up with the government office does not absolve them of their contractual duty. Unless you failed to provide a document or signature that only you, as the owner, could provide, the responsibility for the delay remains with them.
Finally, the issue of the peeling paint is a matter of poor workmanship. The contractor has an obligation to deliver the house free from defects. Your contract likely includes a guarantee or warranty period. The contractor’s refusal to rectify the poor paint job is a breach of this guarantee. Under the law, if a person fails to perform an obligation correctly, it can be done at their expense.
Art. 1167. If a person obliged to do something fails to do it, the same shall be executed at his cost. This same rule shall be observed if he does it in contravention of the tenor of the obligation. Furthermore, it may be decreed that what has been poorly done be undone. (Civil Code of the Philippines)
This gives you the right to have the repainting done by someone else and to charge the cost to SolidBuild Construction. This is directly related to the 10% retention fee you are withholding. In the construction industry, this fee is specifically held back as security to cover the cost of correcting any defects that arise after completion. You are well within your rights to withhold this amount until the peeling paint and any other defects are satisfactorily resolved.
Practical Advice for Your Situation
- Review Your Contract Thoroughly: Carefully re-read the clauses on delays, liquidated damages, change orders, permit processing, and the warranty for workmanship. These terms are the primary law between you and your contractor.
- Document Everything in Writing: If you haven’t already, send a formal written notice to the contractor. Detail the specific delays, cite the penalty clause, and list all the defects, including the peeling paint. Request that they rectify the defects immediately, citing their warranty obligations.
- Quantify the Delays: Create a detailed timeline of the project. Pinpoint the exact dates for each cause of delay. This will help you objectively assess which delays are justifiable and which are the contractor’s fault. This record is crucial for negotiation or any potential legal action.
- Address the Defective Work: Formally demand the contractor to fix the peeling paint at their own cost. If they refuse, inform them in writing that you will hire another contractor to do the job and the cost will be deducted from their final payment, as supported by Article 1167 of the Civil Code.
- Do Not Release the Retention Fee: You are justified in withholding the 10% retention fee. Inform the contractor that the fee will only be released after all corrective work has been completed to your satisfaction, as this is the legal purpose of the retention money.
- Negotiate a Settlement: Based on your documentation, you can negotiate a fair settlement. You might agree to a time extension for the justifiable delays (e.g., a reasonable period for the change orders) but enforce the liquidated damages for the rest of the delay period.
- Consider Professional Mediation or Legal Action: If direct negotiations fail, your contract might contain an arbitration clause, which requires you to settle disputes through the Construction Industry Arbitration Commission (CIAC). If not, you may need to consult a lawyer to explore filing a formal complaint for breach of contract and damages.
Navigating these issues can be complex, but being armed with knowledge of your rights is the first step. Your position appears strong, particularly regarding the defective work and the retention fee. Proceed with formal, written communication to protect your interests.
Hope this helps!
Sincerely,
Atty. Gabriel Ablola
For more specific legal assistance related to your situation, please contact me through gaboogle.com or via email at connect@gaboogle.com.
Disclaimer: This correspondence is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please schedule a formal consultation.