Can I Claim Extra Costs if the Government Caused Delays in My Project?

Dear Atty. Gab,

Musta Atty! I hope you can shed some light on a very frustrating situation I’m facing. My small construction company, Rivera Builders, won a bid to construct a two-story municipal health center in Batangas. We were so proud, but the project has turned into a nightmare. The contract stated a completion period of 180 days, and we were ready to start on schedule.

The problem is, the Local Government Unit (LGU) failed to clear the site. When we arrived, there were still informal settlers on one part of the lot, and we discovered un-relocated water pipes and electric posts right where the foundation was supposed to be. It took the LGU over four months to handle these issues. During that time, my equipment—a backhoe, a cement mixer, and a small crane—sat idle. I also had to keep my project engineer and a skeletal workforce on payroll, which are part of my overhead costs.

I submitted requests for time extensions, which the LGU approved. Now that the project is finally finishing (albeit very late), I’ve submitted a claim for my idle equipment rental costs and extended overhead, which amounts to a significant sum. The LGU is refusing to pay. Their engineer told me that because I agreed to the time extensions, I waived my right to any monetary claim. My contract has a clause that says if they cause delays, I’m entitled to an extension and the associated costs, but they are ignoring it. Am I in the wrong here? What are my rights?

Respectfully,
Mario Rivera

Dear Mario,

Thank you for reaching out. Your situation is unfortunately common in construction projects, particularly with government contracts. It is indeed a frustrating and financially draining experience when delays outside of your control disrupt your operations.

In principle, the contract is the law between you and the LGU. If your contract explicitly allows you to claim for costs incurred due to delays caused by the client (the LGU), then you generally have a valid and demandable claim. The LGU’s approval of your requests for time extensions, especially without imposing any penalties on you for the delay, can be seen as an acknowledgment that the delays were justified and not your fault. Simply put, their argument that accepting an extension automatically waives your right to costs may not hold water, especially if they cannot point to a specific contractual provision that says so.

The Contract is King: Proving Your Right to Claims

The cornerstone of any contractual relationship is the principle of pacta sunt servanda, which means that agreements must be kept. Your contract governs your rights and obligations, as well as those of the LGU. When a dispute arises, the first and most important step is to look at what the contract says.

You mentioned that your contract contains a clause allowing you to claim for costs associated with delays caused by the employer. This is your primary evidence. In legal disputes, the principle of burden of proof is crucial. This means that the person who alleges something has the responsibility to prove it. In your case, you are alleging that you are entitled to payment for extra costs based on a specific contract clause. Your burden is to present that clause and provide evidence for the costs you incurred (e.g., equipment rental agreements, payroll records).

Once you have established this—what lawyers call a prima facie case—the burden of evidence shifts to the other party. The LGU is claiming that you waived your rights or that a different rule applies. It is now their responsibility to prove their assertion. They cannot simply make a verbal claim; they must present documentary proof, such as a different contract clause that explicitly states that accepting a time extension constitutes a waiver of monetary claims. Jurisprudence is clear on this dynamic:

He who alleges the affirmative of the issue has the burden of proof, and upon the plaintiff, the burden of proof never parts. However, in the course of trial, once plaintiff makes out a prima facie case in his favor, the duty or the burden of evidence shifts to defendant to controvert plaintiffs prima facie case, otherwise, a verdict must be returned in favor of plaintiff.

The LGU’s failure to provide you with possession of a clear worksite is a significant breach of its obligations. Standard construction contracts, often based on international templates, recognize this and provide remedies for the contractor. A typical clause would read something like this:

If the Contractor suffers delay and/or incurs costs from failures on the part of the employer to give possession… The Engineer shall, after due consultation with the Employer and the Contractor determine… b) The amount of such costs, which shall be added to the Contract Price…

This kind of provision directly refutes the LGU’s position. It explicitly separates the remedy of a time extension from the remedy of cost reimbursement, treating them as two distinct entitlements arising from the same cause. Furthermore, the fact that the LGU approved your time extensions without assessing liquidated damages (penalties for delay) against you is a powerful, if implicit, admission. It shows that they found your reasons for the delay to be valid and attributable to them, not to any fault of your own.

Should this dispute escalate, you may even be entitled to recover attorney’s fees. An award of legal fees is considered proper in situations where a party is forced to litigate to protect its interests because of another’s unjustified refusal to pay a valid claim.

An award of attorney’s fees is proper when… the defendant acted in gross and evident bad faith in refusing to satisfy the plaintiffs plainly valid, just and demandable claim…

If the LGU is knowingly resisting your claim by invoking a defense that has no basis in your contract, it could be interpreted as an act of bad faith, compelling you to incur further expenses to enforce your rights.

Practical Advice for Your Situation

  • Organize All Documentation: Compile a complete file containing your contract, all correspondence with the LGU (especially your requests for extension and their approvals), detailed records and receipts of your idle equipment costs, and payroll for the extended overhead.
  • Send a Formal Demand Letter: Draft a clear, professional demand letter. Cite the specific contract clause that entitles you to costs. Attach a detailed breakdown of your claim and all supporting documents. State a reasonable deadline for payment.
  • Challenge Their Defense: In your demand letter, formally request that the LGU provide you with a copy of the specific contractual provision they believe supports their position that a time extension cancels out monetary claims. This puts the burden of proof squarely on them.
  • Highlight the Absence of Liquidated Damages: Point out that their approval of your extensions without penalty is an acknowledgment that the delays were not your fault, thereby strengthening your case for reimbursement of costs incurred during that period.
  • Check for an Arbitration Clause: Review your contract for an arbitration clause. Many construction contracts, including government ones, require disputes to be settled through the Construction Industry Arbitration Commission (CIAC), which is a specialized and often faster venue than regular courts.
  • Consult a Construction Lawyer: This is not just a simple collection case; it involves specific principles of construction law. Engaging a lawyer with expertise in this field will be crucial for navigating the process effectively.
  • Do Not Be Intimidated: Government entities sometimes rely on their position to dissuade contractors from pursuing valid claims. Stand firm on your contractual rights, backed by solid documentation.

It is clear from your account that you have a strong basis for your claim. By methodically gathering your evidence and formally asserting your rights under the contract, you stand a good chance of recovering the costs you rightfully deserve.

Hope this helps!

Sincerely,
Atty. Gabriel Ablola

For more specific legal assistance related to your situation, please contact me through gaboogle.com or via email at connect@gaboogle.com.

Disclaimer: This correspondence is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please schedule a formal consultation.

About the Author

Atty. Gabriel Ablola is a member of the Philippine Bar. Gaboogle is his personal blog where he shares legal analysis and commentary on Philippine law, covering areas such as Maritime Law, Corporate Law, Taxation Law, and Constitutional Law.

For professional legal services and inquiries, Atty. Ablola may be reached through ASG Law Partners at www.asglawpartners.com or gca@asglawpartners.com.

Other Posts

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *