Dear Atty. Gab,
Musta Atty! I hope you can shed some light on a very stressful situation I’m facing. I run a small events management company in Cebu, and for a major Sinulog side-event last January, I hired a contractor, “Reliable Builders Inc.,” to construct custom-designed modular stages. Our contract was very clear: the total project cost was PHP 750,000, with a firm delivery and installation date of January 5, 2024. To ensure timeliness, we included a penalty clause stating that for every day of delay, the contractor would be liable for 1/10 of 1% of the total contract price.
Unfortunately, January 5 came and went with no stages delivered. After a week of frustrating follow-ups, the contractor admitted they could not produce the stages according to the agreed-upon technical specifications. They even tried to offer me a much simpler, generic stage design which was totally unsuitable for the event’s theme. With the festival just days away, I had no choice but to formally cancel our contract and scramble to find another supplier, which cost me significantly more and caused immense stress.
Now, I am trying to claim the penalty for the delay as stipulated in our contract. However, the owner of Reliable Builders is arguing that since I cancelled the contract, all its provisions, including the penalty clause, are now null and void. He claims that you can’t enforce a part of a contract that no longer exists. Is this correct? It feels incredibly unfair that they can just walk away without any consequence after causing such a mess. Can I still demand payment for the penalty even though the contract was rescinded? Thank you in advance for your guidance.
Respectfully,
Ismael Roque
Dear Ismael,
Thank you for reaching out. I understand how frustrating and financially damaging this situation must be, especially when you acted in good faith and relied on your contractor’s commitment. It is a common misconception that cancelling a contract wipes the slate clean, and I am here to clarify your rights.
The core of your issue lies in a fundamental principle of Philippine contract law. In essence, the cancellation or rescission of a contract due to a severe breach does not eliminate the breaching party’s liability for damages. The law explicitly allows the injured party, like yourself, to both rescind the agreement and demand payment for damages. The penalty clause you wisely included is the primary mechanism for this. Let’s delve into the legal framework that supports your position.
The Unbreakable Link: Contract Cancellation and Penalty Clauses
Your agreement with Reliable Builders Inc. is what the law calls a reciprocal obligation. You were obligated to pay, and they were obligated to build and deliver the stages. When one party fails to perform their duty, the law provides the injured party with powerful remedies. The primary law governing this is Article 1191 of the Civil Code.
Article 1191. The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should not comply with what is incumbent upon him.
The injured party may choose between the fulfillment and the rescission of the obligation, with the payment of damages in either case. He may also seek rescission, even after he has chosen fulfillment, if the latter should become impossible. (Emphasis supplied)
The language of the law is unequivocal. The right to rescind comes “with the payment of damages in either case.” This means your act of cancelling the contract and your right to claim damages for the breach are not mutually exclusive; they are complementary remedies. The very same failure by your contractor—their inability to deliver the specified stages on time—triggers both your right to rescind the deal and your right to enforce the consequences of their failure, which in this case are the liquidated damages stipulated in the penalty clause.
Your contractor’s argument that the penalty clause is voided along with the rescinded contract is incorrect. A penalty clause, legally known as liquidated damages, is an accessory agreement specifically designed to address a breach. Its purpose is to pre-compute the damages an injured party would suffer, saving them the difficulty of proving the exact monetary value of their loss. It is an undertaking to assume greater liability to ensure performance. As jurisprudence clarifies:
Liquidated damages are those that the parties agree to be paid in case of a breach. … Under Philippine laws, these damages take the nature of penalties. A penal clause is an accessory undertaking to assume greater liability in case of a breach. It is attached to an obligation in order to ensure performance.
Think of it this way: the penalty clause is like a pre-nuptial agreement for your contract. It doesn’t disappear when the relationship (the contract) ends due to a fault; in fact, that is precisely when it becomes operative. To allow a party to escape the penalty by virtue of the very breach the penalty is meant to punish would be absurd and unjust. It would encourage contractors to simply abandon projects they find difficult, knowing they can use the resulting cancellation as a shield against liability. The Supreme Court has firmly rejected this line of reasoning, stating that to accept it would be to:
…[turn] delinquency into a profitable enterprise, enabling contractual breach to itself be the means for evading its own fallout. It is a position we cannot tolerate.
Therefore, the law and established legal decisions are firmly on your side. The rescission of the principal obligation to build the stages does not extinguish the accessory obligation to pay the penalty. The contractor’s failure to perform their primary duty is what activates their secondary duty to pay the agreed-upon damages for that failure. Their belated and unsuitable offer of a different product does not mitigate their liability, as it does not cure their original breach of contract.
Practical Advice for Your Situation
- Review Your Documentation: Gather all relevant documents immediately. This includes the signed contract, your formal notice of cancellation, any email or text correspondence discussing the delays and the contractor’s failure to meet specifications, and the receipts from the new supplier you had to hire.
- Calculate the Penalty: Compute the exact amount of the penalty based on the formula in your contract (1/10 of 1% of PHP 750,000 per day of delay). The delay runs from the agreed-upon delivery date until the date you formally rescinded the contract.
- Send a Formal Demand Letter: Your next step should be to send a formal, written demand letter to Reliable Builders Inc. State the facts clearly, cite the penalty clause in your contract, specify the amount you are claiming, and give them a deadline to pay. Mention that their argument for voiding the penalty clause is contrary to Article 1191 of the Civil Code.
- Stand Firm on Your Rights: Do not be swayed by their incorrect legal interpretation. Your right to rescind and claim damages is a cornerstone of Philippine contract law. You are not being unreasonable; you are enforcing a provision they willingly agreed to.
- Liquidated Damages Simplify Your Claim: The beauty of a penalty clause is that you do not need to prove the exact amount of income you lost or the stress you endured. The clause itself is the proof of the damages agreed upon by both parties.
- Consider Legal Action as a Final Resort: If the contractor ignores your demand letter, you can file a complaint with the proper court. Depending on the final amount, this could potentially fall under the jurisdiction of the Small Claims Court, which offers a more streamlined and less expensive process.
Your situation is a classic example of why penalty clauses are vital in business contracts. They provide a clear, enforceable remedy when one party fails to uphold their end of the bargain. You acted correctly by including one, and you are well within your rights to enforce it now.
Hope this helps!
Sincerely,
Atty. Gabriel Ablola
For more specific legal assistance related to your situation, please contact me through gaboogle.com or via email at connect@gaboogle.com.
Disclaimer: This correspondence is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please schedule a formal consultation.