Dear Atty. Gab,
Musta Atty! I hope you can shed some light on a frustrating situation I’m facing with my small feed supply business here in Batangas City. I recently imported a shipment of soybean meal from a supplier in Ho Chi Minh City, Vietnam. The Bill of Lading clearly stated 50 metric tons, but it also had a note saying ‘Shipper’s load and count’.
The shipment arrived at the Port of Batangas last month and was handled by the local arrastre operator, ‘Batangas Port Services Inc.’ When I finally received the cargo at my warehouse and weighed it using my certified scale, it only came up to 48 metric tons. That’s a significant 2-ton shortage, which represents a substantial loss for my small business, around PHP 60,000 worth.
I immediately filed a claim with Batangas Port Services Inc., providing them with my weighing results and a copy of the Bill of Lading. However, they denied my claim. Their representative told me that because the Bill of Lading was marked ‘Shipper’s load and count,’ the 50-ton figure wasn’t their responsibility, and it was up to me to prove that 50 tons were actually loaded back in Vietnam. They also mentioned something about possible moisture loss during transit for bulk cargo.
I’m confused, Atty. Gab. I always thought the Bill of Lading was the primary document. If the arrastre received the goods from the ship, aren’t they responsible for delivering the quantity stated, or at least proving they didn’t lose it? Who really has the burden of proof here? How can I possibly prove the exact weight loaded in another country after the fact? Any guidance would be greatly appreciated.
Sincerely,
Gregorio Panganiban
Dear Gregorio,
Thank you for reaching out. I understand your frustration with receiving less cargo than expected and facing difficulties with your claim. This is a common issue in shipping, especially with bulk goods, and the legal principles involved can seem counterintuitive at first.
In essence, while common carriers and arrastre operators have duties regarding the goods they handle, the responsibility for proving a shortage, especially its occurrence and extent, initially falls on you, the claimant. When a Bill of Lading includes clauses like ‘Shipper’s load and count’ or ‘Shipper’s weight, quantity and quality unknown,’ it significantly impacts how liability is determined. It means the carrier and the arrastre operator did not verify the shipper’s declaration of quantity at the loading port, and the Bill of Lading figure isn’t conclusive proof of the amount shipped. You generally need more than just the Bill of Lading to establish your claim successfully.
Navigating Cargo Claims: Proving Your Loss When Goods Go Missing
The situation you described touches upon fundamental principles in maritime and commercial law concerning the responsibilities of common carriers and arrastre operators, and importantly, the burden of proof when goods are allegedly lost or short-delivered. While common carriers are generally presumed negligent if goods are lost, destroyed, or deteriorated under their care, this presumption doesn’t automatically arise until the claimant establishes certain facts.
First and foremost, to successfully claim a shortage, you must prove the actual weight or quantity of the cargo loaded at the port of origin (Ho Chi Minh City, in your case) and compare it to the weight or quantity received at the destination (Batangas). Simply relying on the figure stated in the Bill of Lading is often insufficient, particularly when it contains qualifications like ‘Shipper’s load and count’.
The phrase ‘Shipper’s load and count’ (or similar terms like ‘Said to weigh’ or ‘Shipper’s weight, quantity, and quality unknown’) fundamentally alters the evidentiary value of the Bill of Lading. It signifies that the carrier (and subsequently, the arrastre operator who receives the goods from the carrier) merely accepted the shipper’s statement regarding the quantity or weight without independently verifying it. The carrier essentially states they are unaware of the exact contents or weight loaded by the shipper.
“[A]s the bill of lading indicated that the contract of carriage was under a ‘said to weigh’ clause, the shipper is solely responsible for the loading while the carrier is oblivious of the contents of the shipment.”
This principle means the Bill of Lading, under such clauses, is not considered prima facie evidence (evidence accepted as correct until proven otherwise) of the quantity stated. The burden shifts squarely onto your shoulders, the consignee, to provide clear, convincing, and competent evidence of the actual weight shipped from Vietnam.
“[T]he weight of the shipment as indicated in the bill of lading is not conclusive as to the actual weight of the goods. Consequently, the respondent must still prove the actual weight of the subject shipment at the time it was loaded at the port of origin so that a conclusion may be made as to whether there was indeed a shortage…”
Without establishing the initial weight definitively, it becomes impossible to legally ascertain if a shortage occurred during transit or handling by the arrastre operator. Your own weighing at the destination is crucial, but it only establishes the weight received, not the weight shipped.
Furthermore, even if a difference in weight is noted, the nature of the goods must be considered. Soybean meal, being a bulk grain product, is susceptible to weight variations due to factors like moisture loss (desorption) during transit, especially if moving between different climates, and natural consolidation or settling. Philippine law recognizes that carriers or handlers might not be liable for losses arising from the inherent character of the goods, provided they exercised due diligence.
“Common carriers are responsible for the loss, destruction, or deterioration of the goods, unless the same is due to any of the following causes only: … (4) The character of the goods or defects in the packing or in the containers…”
(See Article 1734(4), Civil Code of the Philippines)
The arrastre operator, Batangas Port Services Inc., acts similarly to a depositary. Their primary duty is to take care of the goods received from the vessel and deliver them to the rightful consignee. While they must exercise diligence, their liability generally attaches only for loss or damage proven to have occurred while the goods were in their custody due to their fault or negligence. If you cannot prove the initial weight, or if the discrepancy falls within acceptable tolerances or could be due to the inherent nature of the cargo (like moisture loss estimated for soybean meal over the voyage duration), establishing the arrastre’s liability becomes very difficult.
| Aspect | Claimant’s Burden (Your Role) | Carrier/Arrastre’s Defense |
|---|---|---|
| Initial Quantity | Prove the actual weight/quantity loaded at origin with competent evidence (beyond just the B/L with ‘shipper’s load’ clause). | Rely on ‘Shipper’s load and count’ clause; argue B/L quantity is not verified/binding. |
| Quantity Received | Accurately document the weight/quantity received upon delivery. | May accept consignee’s weight received or present own discharge tally/survey. |
| Cause of Shortage | Show the shortage occurred due to fault/negligence while in carrier/arrastre custody. | Argue shortage existed before discharge, is due to inherent nature of goods (moisture loss, settling), falls within allowable tolerance, or claimant failed to prove initial weight. |
| Evidence | Independent surveys at origin/destination, reliable packing lists, verifiable weight certificates from loading. | Bill of Lading clauses, discharge surveys, evidence of proper handling, expert testimony on cargo characteristics. |
In summary, the ‘Shipper’s load and count’ clause places a significant hurdle. You need evidence beyond the Bill of Lading to establish the weight loaded in Ho Chi Minh City before you can successfully hold Batangas Port Services Inc. liable for the 2-ton difference.
Practical Advice for Your Situation
- Seek Loading Port Evidence: Try contacting your supplier or an agent in Vietnam to see if any independent weight certificate or survey report was generated at the time of loading that could corroborate the 50-ton figure.
- Review Purchase Contract: Check your agreement with the supplier. Does it mention specific weighing procedures at loading or allow for a certain percentage of variance (+/-) in quantity for bulk goods? A 4% difference (2 tons on 50) might sometimes be within contractual or industry tolerances for bulk commodities.
- Assess Natural Weight Loss: Research typical moisture loss percentages for soybean meal shipped in bulk between Vietnam and the Philippines during that time of year. A 2-ton loss might potentially be argued as within natural variance, making the claim harder.
- Document Arrastre Handling: Did you or your representative observe the discharge and handling process by Batangas Port Services Inc.? Any documented proof of spillage, damage, or negligence during their operation would strengthen your claim specifically against them.
- Verify Your Own Weighing: Ensure your weighing process and scale certification are well-documented and unassailable, as this proves the quantity received.
- Cost-Benefit Analysis: Evaluate the cost of potentially hiring surveyors or pursuing legal action versus the value of the 2-ton shortage (PHP 60,000). Sometimes, the cost of proving the claim can exceed the amount recoverable.
- Future Prevention: For future shipments, consider stipulating in your purchase contract the requirement for an independent pre-shipment survey and weight certificate at the loading port, or agree on specific procedures for weight determination acceptable to both parties.
- Negotiate/Mediate: Even if proving the claim legally is difficult, you could attempt to negotiate a partial settlement with the arrastre or carrier, presenting all the documentation you have.
I know this might not be the straightforward answer you were hoping for, Gregorio. Proving cargo shortages under these circumstances requires diligent evidence gathering, often starting from the point of origin. The notation on the Bill of Lading significantly shifts the burden of proof regarding the initial quantity shipped.
Hope this helps!
Sincerely,
Atty. Gabriel Ablola
For more specific legal assistance related to your situation, please contact me through gaboogle.com or via email at connect@gaboogle.com.
Disclaimer: This correspondence is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please schedule a formal consultation.