Scope of Works in Construction Contracts: Defining ‘Additional Works’ and Breach of Contract

TL;DR

The Supreme Court ruled that waterproofing work on a swimming pool, even if requiring a second application after a design change, was part of the original contract scope and not ‘additional work.’ The contractor, Specialty Contracts, breached their agreement by failing to complete the waterproofing as agreed. Consequently, the Court ordered Specialty Contracts to pay Swire Realty for actual damages, costs to complete the unfinished work, and reduced liquidated damages for project delays, clarifying the obligations within construction contracts and the definition of contract scope versus additional services.

When a Splash Turns into a Dispute: Unpacking ‘Additional Works’ in Construction Agreements

Imagine commissioning waterproofing for a condominium project, including a swimming pool, only to find yourself in court arguing whether a necessary second layer of waterproofing for that pool constitutes ‘additional work’ deserving extra pay. This scenario encapsulates the heart of Swire Realty Development Corporation v. Specialty Contracts General and Construction Services, Inc. At its core, this case delves into the interpretation of construction contracts, specifically the scope of work agreed upon, and what constitutes a breach when disagreements arise over what is included versus what is considered an extra service. The Supreme Court was tasked with determining whether the Court of Appeals (CA) erred in finding that waterproofing the swimming pool a second time was beyond the original contract, thus impacting the financial obligations and liabilities of both parties involved.

The dispute began with an Agreement to Undertake Waterproofing Works between Swire Realty (petitioner) and Specialty Contracts (respondent). Specialty Contracts was hired to waterproof Swire’s Garden View Tower condominium project for a fixed price, including the swimming pool area. After initial work, a ‘Site Instruction Form’ mentioned a ‘2nd waterproofing after lightweight concrete topping’ for the pool. When problems arose and Specialty Contracts didn’t complete the work to Swire’s satisfaction within the agreed timeframe, Swire sued for breach of contract. The Regional Trial Court (RTC) initially sided with Swire, awarding damages. However, the CA reversed this, agreeing with Specialty Contracts that the second waterproofing layer was ‘additional work’ entitling them to further compensation. This CA decision prompted Swire to elevate the case to the Supreme Court, arguing that the CA misconstrued the contract and the evidence.

The Supreme Court, in its decision, emphasized that the petition raised questions of fact, which are generally not reviewable in a Rule 45 petition. However, the Court invoked exceptions to this rule, noting discrepancies between the RTC and CA findings, and the CA’s misapprehension of facts. The pivotal point was whether the second waterproofing layer was indeed ‘additional work.’ The Supreme Court meticulously examined the original Agreement, particularly Article I, which defined the Scope of Works. This article explicitly listed the ‘Swimming Pool’ with an area of 234.20 sq.m. as a covered area for waterproofing. The Court reasoned that by agreeing to waterproof the swimming pool, Specialty Contracts undertook all necessary works to fulfill this obligation for the entire specified area. The mention of ‘2nd waterproofing’ in the Site Instruction Form did not automatically transform it into additional work, especially without evidence proving it was genuinely outside the original scope.

Crucially, the Supreme Court highlighted Article VII of the Agreement, concerning Change Orders. This provision stipulated that any changes or deviations from the original plan, including additional works, required written notice and further agreement on pricing. Specialty Contracts failed to invoke this clause, meaning they did not formally claim or negotiate for additional compensation before proceeding with the second waterproofing layer. The Court inferred that if Specialty Contracts genuinely believed it was additional work, they should have followed the contractually agreed procedure for change orders. Their failure to do so weakened their claim that it was outside the original contract scope.

Furthermore, the Supreme Court upheld the concurrent factual findings of both the RTC and CA regarding Specialty Contracts’ breach of contract. It was established that Specialty Contracts only completed 90% of the waterproofing work within the stipulated 100-day period and failed to rectify deficiencies. The Court affirmed the principle that a party breaching a contract is liable for damages. Regarding damages, the Supreme Court agreed with the RTC’s computation of actual damages, including the cost Swire incurred to complete the unfinished work through another contractor, Esicor. The Court adjusted the actual damages to Php 420,000.00, accounting for retention fees and withholding tax, and upheld the Php 124,931.40 for Esicor’s services.

Concerning penalties for delay, Article V of the Agreement stipulated Php 10,000.00 per day of delay. While the delay amounted to 365 days, resulting in a penalty of Php 3,650,000.00, the Supreme Court exercised its power under Article 1229 and Article 2227 of the Civil Code to equitably reduce this exorbitant penalty.

Article 1229. The judge shall equitably reduce the penalty when the principal obligation has been partly or irregularly complied with by the debtor. Even if there has been no performance, the penalty may also be reduced by the courts if it is iniquitous or unconscionable.

Article 2227. Liquidated damages, whether intended as an indemnity or a penalty, shall be equitably reduced if they are iniquitous or unconscionable.

Considering that Specialty Contracts completed 90% of the project and there was no evidence of bad faith, the Court deemed Php 3,650,000.00 unconscionable and reduced the liquidated damages to Php 200,000.00. Finally, the Supreme Court reversed the RTC’s award of attorney’s fees, citing jurisprudence that such awards require clear factual and legal justification, which was lacking in this case. The Court emphasized that merely stating a party was forced to litigate is insufficient grounds for awarding attorney’s fees.

FAQs

What was the central issue in the Swire Realty case? The core issue was whether the second layer of waterproofing for the swimming pool was considered ‘additional work’ outside the original construction contract scope, and whether the contractor breached their contract.
What did the Court of Appeals initially decide? The Court of Appeals reversed the RTC decision and ruled in favor of Specialty Contracts, stating that the second waterproofing was ‘additional work’ and Swire Realty owed them further payment.
How did the Supreme Court rule? The Supreme Court reversed the CA decision, finding that the second waterproofing was within the original scope of work and that Specialty Contracts breached their contract by not completing the agreed works.
What is the significance of ‘Scope of Works’ in this case? The ‘Scope of Works’ clause in the contract was crucial as it explicitly included the swimming pool waterproofing, leading the Supreme Court to conclude that all necessary waterproofing for the pool was part of the original agreement.
What are ‘Change Orders’ and why were they important? ‘Change Orders’ are contractual provisions for modifications or additions to the original scope of work. Specialty Contracts’ failure to use the Change Order process weakened their claim for additional payment.
What damages and penalties were awarded by the Supreme Court? The Supreme Court ordered Specialty Contracts to pay Swire Realty Php 420,000.00 in actual damages, Php 129,931.40 for costs to complete unfinished work, and Php 200,000.00 in reduced liquidated damages for delays.
Why were attorney’s fees not awarded in this case? Attorney’s fees were not awarded because the Supreme Court found that the RTC’s justification—merely stating Swire was forced to litigate—lacked sufficient factual and legal basis as required by jurisprudence.

For inquiries regarding the application of this ruling to specific circumstances, please contact Atty. Gabriel Ablola through gaboogle.com or via email at connect@gaboogle.com.

Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: Swire Realty Development Corporation v. Specialty Contracts General and Construction Services, Inc., G.R. No. 188027, August 9, 2017

About the Author

Atty. Gabriel Ablola is a member of the Philippine Bar. Gaboogle is his personal blog where he shares legal analysis and commentary on Philippine law, covering areas such as Maritime Law, Corporate Law, Taxation Law, and Constitutional Law.